24-92-103. Construction of public projects - competitive sealed bidding.

(1) All construction contracts for public projects shall be awarded by competitive sealed bidding except as otherwise provided in section 24-92-104.

(2) An invitation for bids shall be issued and shall include a project description and all contractual terms and conditions applicable to the public project.

(3) Adequate public notice of the invitation for bids shall be given at least fourteen days prior to the date set forth therein for the opening of bids, pursuant to rules. Such notice may include publication by electronic on-line access pursuant to section 24-92-104.5 or in a newspaper of general circulation at least fourteen days prior to bid opening or in an electronic medium approved by the executive director of the department of personnel.

(4) Bids shall be opened publicly in the presence of one or more witnesses at the time and place designated in the invitation for bids. The amount of each bid and such other relevant information as may be specified by rules, together with the name of each bidder, shall be entered on a record, and the record shall be open to public inspection. After the time of the award, all bids and bid documents shall be open to public inspection in accordance with the provisions of sections 24-72-203 and 24-72-204.

(5) Bids shall be unconditionally accepted, except as authorized by subsection (7) of this section. Bids shall be evaluated based on the requirements set forth in the invitation for bids, which may include criteria to determine acceptability, such as inspection, testing, quality, workmanship, delivery, and suitability for a particular purpose. Those criteria that will affect the bid price and be considered in the evaluation for award shall be objectively measurable, such as discounts, transportation costs, and total or life-cycle costs.

(6) Withdrawal of inadvertently erroneous bids before the award may be permitted pursuant to rules if the bidder submits proof of evidentiary value which clearly and convincingly demonstrates that an error was made. Except as otherwise provided by rules, all decisions to permit the withdrawal of bids based on such bid mistakes shall be supported by a written determination made by the responsible officer.

(7) The contract shall be awarded with reasonable promptness by written notice to the low responsible bidder whose bid meets the requirements and criteria set forth in the invitation for bids. In the event that all bids for a construction project exceed available funds, as certified by the appropriate fiscal officer, the responsible officer is authorized, in situations where time or economic considerations preclude resolicitation of work of a reduced scope, to negotiate an adjustment of the bid price with the low responsible bidder in order to bring the bid within the amount of available funds; except that the functional specifications integral to completion of the project may not be reduced in scope, taking into account the project plan, design, and specifications and quality of materials.

Source: L. 81: Entire article added, p. 1255, § 1, effective July 1. L. 98: (3) amended, p. 1097, § 11, effective June 1. L. 2009: (3) amended, (SB 09-290), ch. 374, p. 2041, § 7, effective August 5.

Editor's note: Subsection (3) was amended in a 2009 act that was passed without a safety clause. The act, or portions thereof, may not take effect if the people exercise their right to petition under article V, section 1 (3) of the state constitution. For further explanation concerning the effective date, see page ix of this volume.

 
ANNOTATION

Law reviews. For article, "The Potential and Perils of Colorado Public Construction Contracting", see 16 Colo. Law. 2131 (1987). For article, "Post-Award Bid Shopping in the Colorado Public Construction Industry", see 18 Colo. Law. 1739 (1989).

 